How it works
Oviously, the transportation of nearly 450,000 tonnes of slurry
pro anno to Maabjerg BioEnergy is a bit of a challenge. We estimate
that transportaion by tanker trucks only would require 40 to 50
truck loads per day.
To reduce traffic and smell Maabjerg BioEnergy has chosen a
combination of pipe lines and road transport. At the moment we are
working at setting up a network of pipelines from the main facility
to a number of hubs for loading/unloading.
Pipeline structure
The pipelines will be constructed in "star formation" from
Maabjerg BioEnergy reaching out 16 km (10 miles). Along the
pipeline a number of hubs will be build, with storage capacity and
facilities for loading and unloading.
The pipeline is made up of two separate lines. One for pumping
slurry into the facility as raw material for the biogas process and
one for returning "de-gassed" slurry to be used as environmentally
friendly (and less smelly) fertilizer.